The grid

What a RACI matrix template is for

Most project arguments in month three are about something nobody wrote down in week one: who was supposed to decide. A RACI matrix template fixes that on one page. Each row is a piece of work, each column is a person or role, and each cell holds one letter saying how that person is involved. The value is not the grid itself; it is the conversation you have while filling it in, which is much cheaper at the start than halfway through.

The method is also called a responsibility assignment matrix or a linear responsibility chart. The four letters mean the same thing everywhere:

LetterMeansHow many per row
R, ResponsibleDoes the workOne or more
A, AccountableDecides, and carries it if it goes wrongExactly one
C, ConsultedAsked before the decision; can change itAs few as you can
I, InformedTold after; cannot reopen itAs many as you like

On a small team one person often both decides and does the work. Our template takes that as A/R, so the grid stays honest without forcing a second name into the row.

Free download

Download the free RACI matrix template for Excel

The workbook has three tabs. RACI matrix is the blank grid: twenty rows of work and six people, with a dropdown in every cell (R, A, C, I or A/R) so a typo cannot slip in. Example is the same grid filled in for a website relaunch, so you can see what a finished one looks like before you start yours. How to read it holds the legend and the warning signs below.

Our free RACI matrix template filled in for a website relaunch, with the check column reading OK on every row
The Example tab: one A per row, and the Check column confirms it.

The column that makes this template different is Check. Paper and most RACI chart templates will happily let you put two A’s in a row or forget the R, and you only find out when the work stalls. Here, every row reads OK, No A, Two A or No R as you type, so the grid checks itself. We built and tested it in Microsoft Excel; there is no macro and nothing to enable.

Filling it in

How to fill in a RACI matrix in five steps

  1. List the work, not the tasks. Rows are deliverables or decisions (“Approve budget and launch date”, “Write launch emails”), ten to twenty of them. A row per small task turns the grid into a to-do list nobody reads.
  2. List the people or roles across the top. Six columns is the width that stays readable. Needing a seventh is a sign the project wants splitting.
  3. Place the A first, one per row. This is the argument worth having out loud: who decides, and who carries it if it goes wrong.
  4. Then the R. At least one per row. If the A also does the work, use A/R.
  5. Add C and I last, and sparingly. Every C is a meeting or a message before anything moves. Ask whether that person can really change the decision; if not, they are an I.

Reading it

Four warning signs in a finished RACI chart

A filled grid is worth reading back as a whole, row by row and then column by column. These are the patterns that mean trouble:

  • Two A’s in a row: nobody is really accountable. Pick one person, and say so in the room.
  • No A in a row: the same problem, and worse, because the row looks finished at a glance.
  • A column that is all C: someone is in every conversation and owns nothing. Give them work or stop inviting them.
  • A row that is all I: nobody is doing it. That is a backlog item, not a project line.

Two A’s in a row means nobody is really accountable.Reading the grid

The Check column catches the first two for you. The column patterns need a person; read down each name once after the grid is filled and before you share it.

Once the grid settles who decides, the meeting record only has to capture what was decided. Our free meeting minutes template uses the same project as its filled example.

Variants

RACI, RASCI and DACI: which chart to use

Several variants add or rename letters. RASCI (also written RACIS or RASIC) adds S for Support, people who help the R without owning the work. DACI swaps the vocabulary for Driver, Approver, Contributors and Informed, and is common for one-off decisions rather than ongoing work. For most project teams, plain RACI with an A/R option covers it; an extra letter is only worth it if you keep arguing about the same gap.

Where it lives

Keeping the RACI matrix beside the rest of the project

A RACI matrix works best next to the plan it describes. If your project runs in a spreadsheet, keep the RACI tab in the same file as the schedule; our project plan template guide and the Google Sheets project management template post cover that side, and more workbooks are collected in our Excel templates roundup.

If your team runs projects in OneNote, our OneNote Project Management Template ($29) has a RACI page built in, with the same letter legend and the same reading table, sitting beside the kanban board, the risk register, the stakeholder map and a comms plan. Our guide to OneNote project management templates walks through how that notebook is laid out.

What is the row your team argues about most when you fill in a RACI chart? Tell us in the comments; the best ones end up in the example tab of the next version.

FAQ

Common questions, answered briefly

What is a RACI matrix template?
A grid with pieces of work as rows and people or roles as columns, where each cell holds R (responsible), A (accountable), C (consulted) or I (informed). It sets out who does the work, who decides, who is asked first and who is told after.
Is there a free RACI matrix template for Excel?
Yes. Ours is a free .xlsx with a blank grid, a filled example and a how-to-read tab, plus a Check column that flags rows with no A, two A’s or no R. No signup and no macros.
Can a task have two accountable people in a RACI matrix?
It should not. The point of the A is that one person decides and answers for the result. Two A’s on a row usually means the decision has not been made, so pick one person before the work starts.
What is the difference between responsible and accountable?
Responsible people do the work; there can be several. The accountable person decides, signs off and carries the outcome; there is exactly one. On small teams one person is often both, written A/R.
What is RASCI?
A RACI variant that adds S for Support: people who help the responsible person without owning the work. It is useful when many contributors sit around one owner; otherwise plain RACI is enough.

If yours isn’t above, drop it in the comments and we’ll add it.

People also ask

Other questions, briefly answered

What goes in a project plan template? Can you manage a project in Google Sheets? How do you run a project in OneNote? Which Excel templates are worth downloading?
Reference Responsibility assignment matrix: the RACI model and its variants (checked November 2026) wikipedia.org