Four builds
Four things Excel calls a timeline, and the one that reads your dates
Ask Excel for a project timeline and you find three different things, none of which is the chart most people picture. The SmartArt timeline on the Insert tab is a drawing: you type each date into a shape, and Microsoft’s steps for moving one are Move Up and Move Down on the SmartArt Design tab. The PivotTable Timeline is not a chart at all. Microsoft describes it as a dynamic filter that lets you filter a PivotTable by date and zoom in on a period with a slider, which is useful on a sales report and no help with a project.
The third is the Gantt chart, and Excel does not have one. Microsoft’s Gantt chart page says so directly, Excel has no predefined Gantt chart type, and shows how to simulate one with a stacked bar chart: chart each task’s start and its length, give the start series No Fill so only the length shows, then set the task axis to categories in reverse order so task one sits at the top.
The stacked bar works for a slide. A running project needs more: a milestone is a task of zero days, so it draws as a bar of zero length, and progress needs another series. The fourth build draws the timeline in the cells themselves, with conditional formatting, and our free file is built on it.
| Build | Reads your dates | Milestones | Best for |
|---|---|---|---|
| SmartArt timeline | No, typed by hand | One shape per date | A one-off slide |
| PivotTable Timeline | Filters them | None | A report by period |
| Stacked bar chart | Yes, two columns | Zero-length bars | A printed status chart |
| Formatted grid | Yes, every cell | A dark cell | A plan you update weekly |
Pick by what happens on the day a date moves. A drawing has to be redrawn, a chart redraws its bars but has nowhere natural to put a milestone, and a formatted grid has nothing to redraw, because the bar is the result of a formula rather than a shape somebody placed.
The file
What the free project timeline template Excel file holds
Four tabs, and you only type on two of them. The timeline is one tab with the tasks, so a task and its bar always sit on the same row and cannot drift apart.
What’s inside
Our free Project Plan Template
- Google Sheets
- .xlsx via File, Download
- Example and blank
Best for one project with up to 300 tasks and one person keeping the dates.
- Task
- Phase
- Who is on it
- Start
- End
- % done
- Progress
- Status
- Milestone
- Goal
- Scope
- Deliverables
- Milestones
- Tasks and owners
- Budget
- Risks
- Changes
- Phases
- Who is on it
4 tabs, 300 task rows, 60 date columnsno chart objects · every rule in Manage Rules
Structure read from both editions’ .xlsx download, 17 November 2026 How to fill the Plan tab
Status is a formula, not a drop-down, so it cannot go stale: a task reads Done at 100%, Not started before its start date, Late once its end date has passed short of 100%, In progress in between, and No dates until both dates are in. The example is a small office move of about three months, and its dates are written relative to today, so whenever you open it the project is mid-flight, sixteen tasks with four done and one late. Type over it, or copy the blank and start from your own first task.
If you run several projects at once, our Project Tracker with Gantt Chart ($39, Google Sheets and Excel) is the step up: one task list across every project, a Health column that marks late starts and overdue work, and progress weighted by each task’s length. It ships as Excel workbooks, blank and filled in, plus Google Sheets copies.
The rule
How to create a project timeline in Excel with one formatting rule
Put the tasks in rows, a start date in one column and an end date in the next. To the right, give each column a date in a header row, the chart’s first day and then the previous date plus one. A grid cell belongs to a task’s bar when the task starts on or before that column’s date and ends on or after it. That sentence is the whole rule.
=AND($E7<=K$4,$F7>=K$4)
The bar rule at one day per column: starts in column E, ends in column F, the column dates in row 4, applied to the grid from K7 with K7 as the active cell.
Formula reviewed 17 November 2026
The dollar signs do the work. Microsoft’s conditional formatting page notes that a formula can evaluate cells outside the selected range and that relative references adjust for each cell in the selection. So $E7 locks the column and lets the row move, which means every cell in a row reads the same task, and K$4 locks the row and lets the column move, which means every cell reads its own column’s date.
-
1
Select the grid, starting at the top-left cell
Every date column and every task row, with K7 (or your first grid cell) active, because the formula is written for that cell.
-
2
Home, then Conditional Formatting, then New Rule
Choose Use a formula to determine which cells to format. Microsoft’s rule is that the formula must return True or False.
-
3
Type the formula, pick a fill, then OK
A mid colour for the bar. Everything else, milestones and today included, is another rule on the same range.
Our file stacks five rules on the grid, and their order is the design. Microsoft’s page explains that rules are evaluated top to bottom in order of precedence, that when two conflict the higher one applies, and that a new rule is added to the top of the list by default. Ours run milestone first, then the share of the bar that is done, then the bar, then weekends, then today, so a milestone always shows dark on top of its bar.
Add the done share as its own rule above the bar: it fills from the start date across the same fraction of the task as the % done column, using $E7+ROUND(($F7-$E7+1)*$G7,0)-1 as the last day it reaches. A bar half dark and half light is easier to read across a room than a percentage in a column.
Milestones
Milestones: a one-day task with a flag, drawn dark
In our file a milestone is an ordinary task row whose start and end are the same day, with Milestone set to Yes from a drop-down. Because the milestone rule sits at the top of the list, the cell for that date takes the darkest colour on the chart instead of the bar colour. The example carries three: the lease signed, the layout approved and move day.
=AND($J7="Yes",$F7>=K$4,$F7<=K$4+$C$3-1)
The milestone rule: Milestone in column J, the end date in F, the column dates in row 4 and the days per column in C3. Keep it above the bar rule in Manage Rules.
Formula reviewed 17 November 2026
The Plan tab lists the first three milestones by name, date and status on its own, read from the timeline with INDEX and MATCH, so the summary someone outside the team reads never needs retyping when a date moves.
If everything is a milestone, the dark cells stop meaning anything.
Which dates deserve the flag? The file’s own advice is the few dates someone outside the team cares about. If everything is a milestone, the dark cells stop meaning anything. A project milestone template in Excel earns its keep when the three or four dark squares are the dates you would put in an email to the person paying for the work.
Scale
Two cells rescale the project timeline from weeks to over a year
A project schedule template in Excel can break at the edge of its grid, when the project outlives the columns. Ours has sixty date columns and two cells at the top left that move them. Chart starts on sets the first column’s date. Days per column sets the step. At one day a column the grid shows about two months; at seven it shows 420 days, well over a year, and every column date rebuilds from those two cells.
Once a column stands for more than one day, the bar rule has to ask whether a task overlaps the column’s span rather than whether it covers one date: the task must start on or before the column’s last day and end on or after its first. With the step in C3, that is =AND($E7<=K$4+$C$3-1,$F7>=K$4), and it reduces to the one-day rule when C3 is 1.
Two smaller rules finish the grid. Weekends are shaded only at one day per column, because a week-wide column has no weekend to shade. And the column holding today is tinted, using TODAY, which Microsoft documents as returning the serial number of the current date. If the tint stops moving from one day to the next, Microsoft’s fix is to check that calculation is set to Automatic under File, Options, Formulas.
The limit
What an Excel project timeline will not do
Dependencies. In our file the tasks do not chain: move one end date and the tasks after it stay where they were, so you check them yourself. That is on purpose. A formula that sets each start to the previous end plus one works for a strict sequence and breaks the moment two tasks run side by side, and a schedule that rearranges itself on rules you cannot see is harder to trust than one that stays put.
The paid Project Tracker goes as far as we think a spreadsheet honestly can: it flags a task that starts before the one it depends on has ended, so a slipped date shows what it knocks on, and leaves the moving to you. With dozens of linked tasks and several people changing dates daily, a dedicated project tool is the better fit.
If your team plans in Google Sheets rather than Excel, our Gantt chart template for Google Sheets guide builds the same grid with Sheets’ own formula, and the project management template guide covers keeping every task in one list. The rest of our free files for Excel are on the Excel page, and the Excel templates guide explains how we judge one before we hand it over.
Dates in two columns, one rule for the bar, one for milestones above it, and two cells for the scale. That is the whole of a project timeline that keeps itself true. Tell us in the comments what your timeline has to survive, a client who moves the deadline or a team that never updates % done, because that is usually where the next rule belongs.
FAQ
Common questions, answered briefly
How do I create a project timeline in Excel?
=AND($E7<=K$4,$F7>=K$4), with starts in E, ends in F and the column dates in row 4. Microsoft’s alternative is a stacked bar chart with the start series set to No Fill. Our free template has the grid built already.Does Excel have a project timeline template built in?
How do I show milestones on an Excel timeline?
Will an Excel timeline update when the dates change?
What is the difference between a timeline and a Gantt chart?